Citi Field
« Previous EntriesCiti Field Update 5/13/08
Tuesday, May 13th, 2008Here is the latest on Citi Field. You can see the most recent pictures on Webshots and the Refugees forum.
Workers recently finished installing the arched steel on top of the CF scoreboard, meaning that the entire structure of Citi Field is now in place. Aside from the laying of bricks, installation of signage, and the completion […]
Citi Field Update 4/12/08
Saturday, April 12th, 2008It’s been an eventful first two weeks of the season for the Mets, and it’s also been an eventful two weeks at Citi Field. You can see the latest pictures on the Refugees forum and Webshots.
On Wednesday, April 9th, the “topping off” ceremony was held at Citi Field. The ceremony, signaling the completion of steel work, […]
Citi Field Update 3/29/08
Saturday, March 29th, 2008Here is this week’s Citi Field update. As always, you can see the latest pictures on the Refugees forum and Webshots.
With only ten days until the Mets home opener, most of the visible changes over the past two weeks have been related to infrastructure work. Work continues at a rapid pace on the new subway […]
New Citi Field interior pictures
Wednesday, March 26th, 2008Chris S., aka islandxtreme26, has taken another great batch of pictures taken inside Citi Field.
Besides giving us a rare view of the interior work, Chris took some nice pictures of the work going on outside of the stadium, as workers get the the new subway exit and the parking lots ready for Opening Day.
You can see the […]
Citi Field Update 3/15/08
Saturday, March 15th, 2008Here is this week’s Citi Field update. Much work has been done over the past two weeks, not only on the ballpark but also on getting the surrounding area ready for fans to return to Shea in just a few weeks. You can see the latest pictures on the Refugees forum and Webshots.
Installation of the arched brick […]
Interior pictures of Citi Field
Wednesday, March 12th, 2008Chris S. has posted an incredible new batch of pictures taken inside Citi Field. See them here.
Citi Field Update 3/1/08
Saturday, March 1st, 2008Here is this week’s Citi Field update. Today’s pictures can be found on the Refugees forum and Webshots.
Over the past two weeks, installation of precast risers for the upper deck seating have been completed and the canopy covers the entire length of the upper seating area. All of the park’s seating areas are now in place, […]
Home Run Apple Update
Friday, February 22nd, 2008Mets COO Jeff Wilpon appeared on WFAN’s Boomer and Carton show this morning, and was asked about the status of the home run apple.
“The apple, as it sits right now, is in not great repair. So we’re probably going to send it out somewhere to get repaired,” Wilpon said. “We’re going to see how much of […]
Citi Field Update 2/19/08
Tuesday, February 19th, 2008A new batch of Citi Field pictures, taken today, can be found on Webshots and the Refugees forum. Also check out StadiumPage.com, where you can find an incredible batch of interior pictures, including shots from inside the rotunda and pictures taken from the upper and lower concourses.
Work continues at a rapid pace on the Jackie […]
Citi Field Update 2/3/08
Sunday, February 3rd, 2008A new batch of Citi Field pictures, taken yesterday, can be found on the Refugees forum and Webshots. Here is the latest on the construction:
Work continues on the Jackie Robinson Rotunda, where the arched brick facade is currently be installed inside and outside. Installation of steel decking for the club and promenade levels above the rotunda, […]