Citi Field Update 5/13/08

By Dan M. | May 13, 2008

Here is the latest on Citi Field.  You can see the most recent pictures on Webshots and the Refugees forum.

Workers recently finished installing the arched steel on top of the CF scoreboard, meaning that the entire structure of Citi Field is now in place.  Aside from the laying of bricks, installation of signage, and the completion of a small portion of facade along the first base line (where a construction elevator is currently attached), what you see now as you walk by Citi Field is what you will see over the next fifty years.

Installation of seats continues in the upper portion of the promenade level.  Installation of seats has recently begun in the lower promenade level seats and the RF “Pepsi Porch.”

Work is progressing at a rapid pace on all of the interior areas of the ballpark, including the administration building, rotunda, concourses, clubhouses, and luxury suites.  As Citi Field nears completion, the majority of work will be done on these interior areas, and will not be visible to fans walking around outside the park.

Check back soon for the next Citi Field update.